1. What is a Milestone in a project?
A milestone is a reference point that marks a major event in a project and is used to monitor the project's progress. Any task with zero duration is automatically displayed as a milestone. You can also mark any other task of any duration as a milestone.
2. What is a critical task in a project?
Tasks which cannot be delayed without affecting the project finish date are the critical tasks. A Critical must be completed on schedule for the project to finish on time. If a critical task is delayed, the project completion date might also be delayed. A series of critical tasks makes up a project's critical path.
3. What information can help me analyze my projects progress?
Five pieces of task information help to analyze the project progress:
- Duration
- Work
- Start date
- Finish date
- Cost
Variations of each of these types of fields help you compare and evaluate your progress.
4. What is the difference between Lead time and Lag time?
Lead time: An overlap between tasks that have a dependency.
Lag time: A delay between tasks that have a dependency. For example, if you need a two-day delay between the finish of one task and the start of another, you can establish a finish-to-start dependency and specify a two-day lag time